WestConnex M4/M5 Link, NSW

Antec Fire was engaged to support WestConnex’s M4/M5 Link with fabricated deluge systems and emergency response gear, supplied as complete off-site packages.

Location

WestConnex M4/M5 Link, NSW

Scope

  • Fabrication and supply of deluge manifolds
  • Fabrication, fit out and supply of Emergency Equipment Cabinets

Background

This underground motorway link required modular infrastructure that could be quickly deployed with minimal on-site disruption.

 

Challenge

Antec Fire needed to fabricate large components in parallel while staging production to support the contractor’s evolving schedule.

 

Solution

We fabricated deluge manifolds to project specifications and built Emergency Equipment Cabinets with full internal assemblies ready for delivery.

 

Implementation

Components were batch produced and delivered per tunnel segment to coordinate with construction timelines.

 

Benefits / Results

  • Modular delivery of infrastructure elements
  • Reduced on-site assembly and installation
  • High compliance with project standards

Key take-aways

Parallel fabrication enables just-in-time delivery for large tunnel projects.

 

Why this project matters for Antec

Demonstrates our ability to produce core tunnel fire systems with speed, precision, and a modular mindset.